The Newton–Weston bridge programme at the I-90/I-95 interchange in Massachusetts includes demolition of the existing westbound structure and reconstruction of approach roads in its 8–21 November look-ahead. MassDOT also lists substructure work, noise-wall foundations and mechanically stabilised earth wall construction.
United StatesAlternating lane closures on I-90 and I-95 are scheduled between 9 and 20 November. The notice says no activities are scheduled for the Veterans Day holiday on 11 November. It also lists deck repairs and joint demolition on the ramp bridges carrying traffic between the highways.
Why it matters
The look-ahead places demolition, new foundations and repairs on adjoining structures in the same work area. For road users and deliveries, the changing lane arrangements are part of that sequence and need to be checked against the current travel notice.
MassDOT construction look-ahead for 8–21 November 2026
Featured photograph. Reconstruction of the Weston interchange in October 2026. Photo: Pi.1415926535 (CC BY-SA 4.0).