Work on Dubai’s Al Mustaqbal Street development has exceeded 70% completion, according to an RTA update reported by Emirates News Agency on 20 November. Three tunnels, totalling 1,500 metres at the Al Mustaqbal–Trade Centre Street intersection, are forecast to be ready by February 2027.
Middle EastThe update places the AED633 million street project alongside the AED696 million Trade Centre Roundabout development. The latter’s final bridge opened in October. These are different milestones within an integrated road programme serving Dubai World Trade Centre and neighbouring districts.
RTA projects that the completed tunnels will reduce average intersection delay across the approaches from around 12 minutes to 90 seconds. This is a forecast for the completed works, not an independently verified current traffic result.
Why it matters
The construction challenge includes working around an active exhibition calendar. Access for visitors, venue servicing and traffic passing through the district can place different demands on the same road network.
Civil Insight’s assessment is that effective staging needs to account for those demands at different times of day. For the built environment, the quality of the connection between the highway, local streets and venue entrances matters alongside the capacity of individual bridges or tunnels.
The February target should remain distinct from the earlier bridge openings when reporting programme progress.
Source: Emirates News Agency’s RTA programme update, 20 November 2026.