Geotechnical borehole drilling for stage 2 of Melbourne Airport Rail is scheduled to begin in Sunshine North on Monday 23 November 2026. A Victoria’s Big Build notice issued on 20 November places the investigations on council land near the railway at Bunnett Street.
AustraliaThe programme runs to Friday 18 December. A drilling rig, small trucks and excavators will be used to investigate ground conditions in preparation for major construction. The notice identifies possible low-level noise and additional construction-vehicle movements.
Published standard working hours are 7 am–6 pm Monday to Friday and 7 am–1 pm on Saturdays. The notice’s map identifies the investigation area; it should be used rather than assuming the whole rail corridor is affected.
What the investigations contribute
Ground investigation is an early construction input whose value often becomes visible later. Borehole information can help the design team understand the ground at the sampled locations and decide whether further investigation is needed. It does not, by itself, certify conditions everywhere along an alignment.
For site teams, the immediate issue is coordinating investigation access with the surrounding road, rail and public environment. A relatively small rig still brings vehicle movements, working space and local interfaces that need to be planned.
This is an investigation programme, not an announcement that stage 2 major construction has started or that its final design is complete.
Source: Victoria’s Big Build works notice, 20 November 2026.