28 November 2026 — Network Rail’s £9 million programme at Inverness station and on the railway to Kyle of Lochalsh is scheduled to start on 28 November, following a passenger reminder issued on 27 November.
United KingdomTrack renewal shares access with bridge and drainage work
The line between Dingwall and Kyle of Lochalsh is scheduled to close through 18 December, with trains due to return on 19 December. Replacement buses are planned between Inverness and Dingwall/Kyle of Lochalsh during the works. Passengers should check the operator’s arrangements before travelling.
At Inverness, the scope includes replacing track and sleepers at platforms 5 and 6 and equipment that enables trains to change tracks. Around seven kilometres of track will be renewed across several locations. Culvert renewals and work at railway bridges, including Carron Viaduct, are also included.
Why it matters
For railway construction teams, the programme is an example of combining asset disciplines within one access window. Track renewal, drainage work and bridge repairs have different work fronts and resources, but share the constraint of returning a functioning railway to service.
The drainage element is particularly relevant to resilience: the programme addresses the route around the track as well as the track itself. Network Rail expects the work to support long-term reliability. The published return date remains a programme commitment to follow, rather than evidence that the works have already been completed.
Source: Network Rail’s 27 November 2026 works reminder.
Featured photograph: Inverness station, August 2025. Archive station photograph, before the November–December 2026 renewal works. Photo: Sneeuwvlakte, CC BY-SA 4.0.



