Rogers Road Grade Separation Selects Contractor as Utility Work Continues

/ Ali Eskandari

Blythe Construction has been selected for the Rogers Road Grade Separation project in Wake Forest, North Carolina. A Town of Wake Forest notice published on 20 November 2026 relays an NCDOT update issued on 18 November.

NCDOT aerial project visualisation showing the proposed Rogers Road bridge over the CSX S-Line, Wake Forest, North CarolinaUnited States

Main construction is anticipated after the new year. The activity currently visible is utility work, according to the update. An on-site detour is planned throughout the project to maintain access along both sides of Rogers Road, with its alignment changing as construction phases progress.

The project team is adding maps to its public information page to explain those phase-specific routes. The stated start remains an expectation, rather than confirmation that main construction has begun.

NCDOT’s P-5707 project will replace the existing at-grade CSX S-Line crossing with a road bridge at the same location. The planned road design includes additional traffic lanes and footpaths. NCDOT announced a roughly US$40 million construction contract award in October; the November update clarifies that the work visible now is utility relocation rather than the main bridge build.

Why it matters

Utility relocation and main civil construction can appear to the public as one continuous worksite, even when they operate under different sequences and constraints. Clear communication about which stage is underway helps residents and businesses interpret what they see.

Civil Insight’s assessment is that a changing on-site detour needs to be treated as part of the construction sequence. Maintaining access involves more than installing signs: the route, work areas and transitions between phases must remain understandable to the people using the road.

The current notice does not establish a final completion date or confirm that the detour has already changed. Readers should use the project page for subsequent traffic updates.

Source: Town of Wake Forest, 20 November 2026; NCDOT project information; NCDOT contract announcement, 28 October 2026.